Is analytical testing required at product changeover, on equipment in shared facilities, following completion of cleaning validation?
QualisteryLevel 2
Is analytical testing required at product changeover, on equipment in shared facilities, following completion of cleaning validation?
Share
Analytical testing is expected at each changeover unless justified via a robust, documented Quality Risk Management (QRM) process.
The QRM process should consider, at a minimum, each of the following:
– the repeatability of the cleaning process (manual cleaning is generally less repeatable than automated cleaning);
– the hazard posed by the product;
– whether visual inspection can be relied upon to determine the cleanliness of the equipment at the residue limit justified by the HBEL.